Timber frame, block or ICF: choose a build method
Compare timber frame, cavity block and insulating concrete formwork. Check the specification, installer, schedule and complete quote before choosing.
The order a self-build usually follows in Ireland, from site and planning through Building Control notices and drawdowns to the completion certificate.
Not sure what comes first? Read where to start. Start by checking the site and your budget, then get planning permission, arrange finance and prepare the detailed design before building. Plan inspections and completion paperwork from the outset so you can draw down the mortgage and move in when the house is ready.
| # | Stage | Before moving on | Payment or paperwork |
|---|---|---|---|
| 1 | Find and check a site | Site can get planning, a wastewater solution and a safe access | Deposit, solicitor, site survey |
| 2 | Design and planning permission | Final grant of permission, after the appeal process | Planning fee, design fees |
| 3 | Arrange finance and budget | Mortgage offer, detailed design and priced tender | Budget, construction drawings, appointments |
| 4 | Insure the build | Agreed cover starts by the first day on site | First premium, lender’s insurance evidence |
| 5 | Notify Building Control | Commencement notice lodged and valid | Notice fee, certificates or opt-out declaration |
| 6 | Build | Each stage inspected | Staged drawdowns |
| 7 | Completion and handover | Completion evidence, final Building Energy Rating (BER), utilities and home cover | Check final drawdown and contract payment conditions |
Stages overlap in practice. Utility applications start during stage 2 or 3, and tender often runs alongside the mortgage application in stage 3. Before starting, obtain the final planning grant and meet its pre-start conditions. Lodge the Building Control notice within the legal time limit and confirm the submission requirements with your local authority. Your design team and lender may need additional steps, so agree who will provide each document. The notice and certification duties come from the Building Control Regulations 1997, as amended.
Find a site, then test it before you commit. Check local housing need rules, access, services, and whether a wastewater system will work using a site suitability assessment. Set a first budget with contingency at this point, because it decides what you can design.
Make your offer on the site conditional where you can, for example on planning permission or on a satisfactory site suitability assessment for wastewater. A site that cannot take a house is worth much less than the price of a site that can.
Appoint a designer, agree a brief, and apply for permission. Use the planning permission guide to check the site and prepare the application. Allow for conditions, and for the possibility of objections and appeals. Permission lasts a fixed period, so note the expiry date: see permission duration.
Start the utility conversations now. Send a pre-connection enquiry to Uisce Éireann early if you need mains water or wastewater services. Its answer can affect the planning submission. Apply for the connection itself once planning permission is secured. If you are in a rural area with a private well and treatment system, this does not apply and the wastewater guide is the relevant one.
Discuss the self-build mortgage early, then supply permission and costings as your lender requires. Understand staged drawdown before you sign. Price the detailed design and check how you will fund costs between mortgage releases.
Have your designer prepare construction drawings and a specification, then ask builders to price the same work. Decide whether you will project-manage or hire a main contractor, and see choosing a builder and contracts and architect or engineer for the appointments.
If you use statutory certification, agree who will take each of these roles before submitting the Building Control forms:
Do not leave these appointments until the week before you start. Appoint the builder before submitting the notice. If you use statutory certification, appoint the assigned certifier too. The opt-out route is explained below.
Arrange insurance before work starts. Check the insurance your lender requires before the first drawdown. If you plan to project-manage yourself, read insurance when you project-manage first.
Before work starts, a commencement notice is lodged with the local authority’s building control section. Submit it through the Building Control Management System (BCMS), or on the prescribed form, as required by article 9 of the Building Control Regulations 1997. Each party to the notice, including the owner, designer, builder and assigned certifier, needs to register on the system first.
Timing. Article 8 requires notice not less than 14 and not more than 28 days before commencement. That window is measured from giving notice, not a fresh 28-day period starting at validation. Confirm that your notice is valid and your intended start date fits the window; ask Building Control what to do if the date changes. The separate seven-day-notice procedure concerns work requiring a fire safety certificate; it is not a shortcut for an ordinary one-off house.
What goes with it. For a new dwelling using statutory certification, include the following documents under article 9(1):
The opt-out route. If you are building one new house on a development containing only that house, or extending a dwelling, article 9(5) allows you to submit a Declaration of Intention to Opt Out of Statutory Certification. This replaces the statutory design certificate, assigned-certifier notices and undertakings, and preliminary inspection plan. The notice of assignment of the builder is still needed. The other compliance plans, particulars, builder assignment and fee remain required. A valid declaration entered on the register removes the Article 20F statutory completion-certificate requirement. The owner still has to ensure compliance with the Building Regulations and should arrange competent design and inspections. Ask your lender, solicitor and insurer whether they will accept it before you choose it: a lender or a later buyer may not. See also structural defects cover, which depends on independent inspection.
Changes after lodging are time-limited: article 9(3) requires the owner to tell the council within 14 days if the assigned certifier or builder changes, and article 9(4) says the same of a change of owner before completion.
Most houses follow this sequence:
Construction stages, contractor payment dates and mortgage releases need to be coordinated; they are not automatically the same points. The assigned certifier works from the inspection plan lodged with the notice. If you ask for a change that affects it, have the plan updated, so that the completion certificate describes what was built.
Utilities during construction. Allow time for water connections: Uisce Éireann’s average is 16 weeks from application to a connection offer, followed by an average of 12 weeks from securing a road opening licence to completing the connection. These are separate stages, and neither time is guaranteed. Apply early rather than waiting for the finished house. Apply to ESB Networks for the electricity connection through its online new-connections process, and arrange the validated electrical completion certificate through your registered electrical contractor and their regulatory body before connection work begins. Keep your own copy.
At the end, the assigned certifier and the builder sign the certificate of compliance on completion, and the certifier lodges it with the council. Under article 20F:
That last point is the one self-builders miss. Moving in before the certificate is registered breaks the Regulations, whatever your lender or insurer says. Where you used the opt-out declaration, article 20F does not apply, but the practical issues at sale and mortgage stage remain.
Walk the house with your certifier and list defects before you pay the last of the contractor’s money. The snagging guide has a checklist. Confirm the lender’s final-drawdown evidence separately from the contract’s final-payment conditions, including retention (money held back under the contract until the agreed conditions are met). A certificate does not by itself settle every snag or trigger every payment.
Connect utilities and, for a new dwelling within the BER rules, get the final Building Energy Rating (BER) certificate and advisory report before first occupation. A provisional BER assesses an unfinished design; it is not limited to homes sold off plans. A final certificate normally lasts 10 years unless a material change affects energy performance. See the BER guide for exemptions and details. Check that your insurance changes from contract works cover to a standard home policy at the point agreed in writing with your insurer, avoiding any gap, and tell your lender the house is complete.
| Person | Role in the process | What you should have from them |
|---|---|---|
| Owner (you) | Lodges the commencement notice, pays fees, holds the finance | Copies of the notice, the council’s validation and every certificate |
| Designer | Signs the certificate of compliance (design) | Construction drawings and a specification that match the planning grant |
| Assigned certifier | Writes the inspection plan, inspects, signs on completion | The inspection plan, stage inspection records, and the completion certificate |
| Builder | Undertakes to build in compliance and signs the completion certificate | A contract, schedule and the stage dates your lender needs |
| Lender’s valuer or engineer | Confirms each stage before a drawdown | A stage report you can send to the bank |
| Council | Validates the notice, registers the completion certificate | Written confirmation of both |
The same professional may report to your lender and act as assigned certifier if appropriately appointed. These remain separate jobs. The roles in this table describe the statutory route; agree suitable independent evidence and inspections if opting out. The lender’s inspection protects the lender’s money, while your certifier is responsible under the Regulations for the inspection and certification of the works. Do not assume one replaces the other.
The inspection plan lodged with the commencement notice decides this, so ask for it in advance and read it. Discuss the following examples of work that may need inspection before it is covered. Your team must set the inspection stages and responsibilities for your particular house. There is no statutory minimum number of visits in this checklist:
Keep dated photographs of each hidden element yourself. They cost nothing and are useful if a defect appears years later, or if a buyer’s engineer asks questions. A claim under structural defects cover is also easier to make when the stage records exist.
This example follows a house built by a main contractor using statutory certification. The construction and appointment dates are invented to show how a schedule fits around the legal notice periods; they are not typical durations or a promised completion date. Allow more time if a certificate is invalid or the council raises a query. For your own schedule, consider how long a self-build takes.
| Week | Event |
|---|---|
| 0 | Planning decision issued. Four-week appeal period begins. |
| 4 | No appeal assumed; wait for the final grant. Apply to Uisce Éireann (if connecting to mains water) and to the lender. |
| 10 | Mortgage offer received. Builder, designer and assigned certifier confirmed. |
| 20 | Commencement notice lodged, 14 to 28 days before the planned start. |
| 24 | Notice assumed valid. Foundations begin within 28 days of giving notice. |
| 24 to 60 | Construction, with inspections and drawdowns at each stage. |
| 60 | Certifier and builder sign the certificate on completion. Lodged with the council. |
| 63 | Assume valid certificate registered within the ordinary 21-day period. Final BER issued. |
| 64 | Final drawdown, move in. |
Apply to Uisce Éireann at week 4. Based on the current 16-week average, you might receive a water connection offer around week 20. Allow for a longer wait.
Keep a copy with a person responsible and a due date beside each task. Your professionals, lender and council will have requirements specific to your house.
Finding a site and checking it is suitable. Check planning prospects, access, services and a workable wastewater solution before committing to a purchase.
Yes. Building Control requires a commencement notice before work starts, and you must meet any conditions in the grant. Your lender will also want conditions satisfied before the first drawdown.
In stages. The lender sets the stages and evidence needed for each release; confirm these in your mortgage offer. See the staged drawdown guide.
Where statutory certification applies, the completion certificate must be registered before occupation. A valid registered single-dwelling opt-out removes that statutory certificate requirement. Final mortgage payment depends on your lender’s conditions.
Last reviewed 21 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.
This guide is general information about self-building in Ireland, not financial, legal or insurance advice. Get advice that fits your own situation before you make decisions.