How insulation and airtightness are installed and tested in an Irish self-build, what a blower-door test measures, and what to check before plasterboard.
Insulation and airtightness decide how warm the house is and what it costs to heat. They are also the work most often hidden and most often done badly, because they happen when many trades are working in a crowded shell and everything is about to be covered. Below: what the installers do, what the test measures, and what to check before plasterboard goes on.
The design sets the thickness and type for each part of the building envelope, and an energy calculation shows that the whole house meets Part L. Typical locations are:
Check that the product, thickness and fixing method match the specification. Insulation that is squashed, wet, gapped or left out around pipes performs far worse than the label. In a timber frame, insulation must fill the cavities with no voids. In a cavity wall, partial-fill boards must be fitted tight and held by retaining clips, and the cavity kept clear.
Most of the heat-loss calculation for a modern house is about junctions rather than flat walls, because the flat parts are already well insulated. That is why a good drawing and a photograph of the junction before it is covered matter more than the headline thickness of insulation.
A thermal bridge is a route where heat bypasses the insulation: a concrete lintel, a steel beam, a wall-floor junction, a poorly insulated window reveal. They cause cold spots, condensation and mould as well as heat loss. The detailing drawings should show how each junction is insulated. Ask your designer to point out the three most important junctions on the drawings, then check those on site.
Airtightness is a continuous barrier that stops air moving in and out through the structure. In a masonry house it is often the internal plaster (wet plaster) or a membrane, while in a timber frame it is usually a membrane taped at every joint. It is only as good as its weakest gap.
Typical leakage paths are:
Ask your builder to use airtight grommets and tapes for penetrations and to seal back boxes. Decide this before first fix. See first fix.
A blower-door test fits a calibrated fan in an external door opening. The house is depressurised and the fan measures how much air flows through the leaks. A result is given as air permeability (cubic metres per hour per square metre of envelope at 50 pascals). A lower number means a tighter house.
If the result misses the target, the designer should recommend where to look and a retest. The cost of leak-hunting, repair and retesting depends on your contract, so agree who pays before the test.
A leaky house breathes by accident. A tight house must breathe by design. Part F of the Building Regulations requires adequate ventilation, and the design should say whether you use background vents with extract fans, demand-controlled systems, or a whole-house heat recovery ventilation system. Check:
See building regulations for self-builds and nZEB and Part L.
Do this before the plasterboard and before the next trade covers the layer. Ask the certifier to inspect the same elements and note the date.
Put the test in the contract. Say who arranges it, who pays for the first test and for retests, what number counts as a pass and what the builder must do if the house misses it. Without this the discussion starts after the failure, when everyone has already moved on.
The designer specifies the target and details. The builder or the specialist installs the insulation and membranes, and is responsible for workmanship. The tester measures the result. The BER assessor uses the test result in the final rating. The certifier checks the stage inspection and the completion paperwork. In a self-managed build, you are the one who coordinates the trades. See assigned certifier explained.
This stage is rarely a separate lender payment, but your builder may link a payment to it. The pre-plaster test is a useful condition: make it a hold point in your contract. See choosing a builder and contracts.
Insulation and membranes are flammable or easily damaged, and fire during the build is among the most expensive losses. Check smoking rules, hot-work procedures and temporary heating on site. Make sure cover includes fire damage to the works and materials, and the cover checker at /cover/ shows the types to ask about.
A fan is fitted into an external door frame, the house is depressurised, and the equipment measures how much air flows through gaps in the building envelope. The result is expressed as air permeability, in cubic metres of air per hour per square metre of envelope at a set pressure.
Many designers recommend a test when the airtightness layer is finished but still accessible, as well as a final test at completion. A pre-plaster test lets you find and fix leaks before they are closed in.
Insulation slows heat flow through materials. Airtightness stops air moving through gaps. A house needs both, because air leaks carry heat away even through well-insulated walls.
Yes. A tight house needs controlled ventilation to remove moisture and stale air. The design must include it. See the ventilation requirement in Part F of the Building Regulations.