The certificate of compliance on completion for an Irish self-build: who signs it, what goes with it, the 21-day check and the single-dwelling opt-out.
Get your certificate of compliance on completion entered on the building control register before you move in, if your self-build uses statutory certification. Agree the submission date and document checklist with your assigned certifier well before the house is finished.
The certificate is a statutory statement, signed by the builder and assigned certifier, that the house was built to the Building Regulations. It is separate from your snagging list and does not guarantee that the house has no defects. Your lender, warranty provider and solicitor may require their own completion evidence. Check their requirements alongside those of your building control authority.
Article 20F of the Building Control Regulations (part of the Building Control Amendment Regulations, BCAR, the standard “statutory certification” route where you appoint an assigned certifier) requires you to submit the certificate to the building control authority and have its relevant particulars entered on the register before the works or building may be opened, occupied or used. The Building Control (Amendment) Regulations 2014 (S.I. 9/2014) introduced this rule from 1 March 2014. It applies to:
Single-dwelling exception: S.I. 365/2015 inserted Article 20F(10). Where a valid Declaration of Intention to Opt Out of Statutory Certification is on the public register for a new single dwelling on a single-unit development, or a domestic extension, Article 20F does not apply. The declaration is submitted at commencement; it is not a way to skip missing completion paperwork at the end. Building Regulations still apply. Agree alternative compliance evidence with your professional adviser, lender, insurer and solicitor.
On the statutory route, your commencement notice includes design documents and undertakings from the certifier and builder. At completion, those two people supply and sign the completion certificate. Submit it through the Building Control Management System (BCMS) and wait for registration before occupation. Ask your council who it expects to upload the documents; agree that responsibility with your certifier.
The certificate must be in the standard form set out in the regulations and accompanied by:
The certificate is signed by the builder and the assigned certifier. That is why a change of either must be recorded on the register within 14 days: the people who sign must be the people on the register. See assigned certifier explained.
Ask which of these records your certifier needs for submission, and keep them in your own house file:
The further records needed depend on the work and the certifier’s requirements. Ask your certifier for their checklist well before completion.
When the authority receives the certificate it records the date and then considers whether it is valid. Article 20F(4) gives it 21 days from receipt to decide, looking at:
If it thinks the certificate may not be valid, it may within the same 21 days write to the person who submitted it, giving reasons, either rejecting it or requiring a revised certificate or additional documents (paragraph 5). Where more documents are required, once everything has arrived the authority may take a further 7 days to consider validity (paragraph 6(ii)).
If it is valid, the authority must enter the particulars on the register within 21 days of receipt and tell the person who submitted it.
If you need registration by a particular day, the regulations allow you to nominate a date. This might be your target move-in date or a date agreed with your lender. There are two submission deadlines:
For an illustrative timetable, assume you plan to move in on Friday 5 March and nominate that date:
| When | What to arrange |
|---|---|
| 29 January to 12 February | Your certifier submits the as-built documents and implemented inspection plan, 5 to 3 weeks before the nominated date |
| By 4 March | The valid certificate must reach the authority |
| 5 March | The authority is ready to enter the particulars on the register, provided the nominated-date requirements are met |
If instead you lodge everything on 1 March, you rely on the standard 21-day period, so the register may not show it until 22 March. For a project subject to Article 20F, wait for registration before occupation. Confirm cover and drawdown conditions separately.
These dates are an example, not a promise of registration on a particular day.
Paragraph (9) says a certificate may refer to works, to buildings including areas within a building, or to developments including phases. If proposing phased occupation, agree the scope and compliance evidence with your certifier and building control authority; do not assume an unfinished house can be occupied merely by naming a phase. The areas must be clearly identified on the certificate and, after validation, on the register.
Failure to comply with Part IIIC, which contains the completion-certificate rules, is an offence under Article 6A and section 17(2) of the Building Control Act 1990. Article 6A also covers Parts II, III, IIIA and IIIB. The original Act printed fines in sterling; those amounts have been revised. Ask your solicitor about current penalties rather than relying on the original figures.
Also check the consequences for the money, cover and documents you need:
Ask your certifier:
Ask your builder:
Check the actual payment terms rather than assuming registration and payment happen together. If your contract does not link them, see choosing a builder and contracts.
A certificate signed by the builder and the assigned certifier, lodged with the building control authority, that the building was built in accordance with the Building Regulations. It lists how the finished house differs from the design filed at the start.
On the statutory certification route, yes. A qualifying single dwelling with a valid registered opt-out is exempt from Article 20F. Otherwise, Article 20F says the certificate must be submitted and its particulars entered on the register before the building may be opened, occupied or used.
The authority must consider validity within 21 days of receipt and, if it is valid, enter it on the register within 21 days. If more documents are required, it has a further 7 days once they arrive.
The builder and assigned certifier supply and sign it, and it is uploaded on the Building Control Management System. A council may expect a particular person to lodge it, so check locally.
Record changes and have their compliance checked; the certificate does not regularise unauthorised work. List them in its annex so the register shows how the house as built differs from the design filed at commencement.
Last reviewed 19 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.
This guide is general information about self-building in Ireland, not financial, legal or insurance advice. Get advice that fits your own situation before you make decisions.