What first fix means in an Irish self-build, who does it, what to photograph and check before plasterboard covers it, and what goes wrong.
First fix is the hidden half of the services: the cables, pipes, ducts and boxes that run inside walls, floors and ceilings. Once plasterboard goes up, you cannot see them again, so this is the stage where a few hours of checking and photographing saves you the most trouble. It is also where the trades overlap most, and where a missed detail causes expensive rework.
Put these decisions in writing, with a marked-up plan, and have each trade confirm it. A verbal “that will be fine” at the stud wall is the commonest source of dispute later.
The aim is a record you can read in five years’ time. A photograph of a bare stud wall with a tape showing “1.2 m” beside a cable tells a future electrician exactly where it is safe to drill. A photograph without scale, or taken after the insulation is in, tells them very little.
Take a photograph of every wall and ceiling run with a tape in view before it is closed. Label them by room. At minimum:
Check the following with the trades:
A new home built to the nearly zero energy building standard (nZEB) typically has a renewable energy source, and a heat pump is a common way to meet it. A heat pump works best with low-temperature emitters such as underfloor heating or larger radiators, and with good insulation and airtightness. Decide the position of the outdoor unit, the cylinder and any buffer tank at this stage. See nZEB and Part L. Check the VAT treatment of the installation with Revenue before you agree the contract.
First-fix problems are cheap to fix on the day and expensive three weeks later. The pattern is nearly always the same: a trade works from an old drawing, a change is agreed on site and not passed on, or one trade cuts through another’s work.
Keep the order of work in mind when you ask for a payment to be released. Some builders bill first fix as one lump when the electrics, plumbing and heating are all in, others bill each trade separately. Agree this in the contract rather than when the first invoice arrives.
First fix is sometimes a separate stage payment, often tied to completion of services before plastering. Check with your builder and lender. See staged drawdown explained.
By now the house contains valuable copper, cable and pipework, and electrical work is an ignition risk if left unfinished. Check that contract works cover includes materials stored on site and not yet fitted, and that your liability cover continues. A leak during testing can damage finished surfaces if some are already in place. Look at insurance when you project manage and the cover checker.
You have a dated, written list of any changes made on site, so the as-built drawings can be corrected.
The electrician has said what the consumer unit capacity is and whether it has room for a car charger or solar later.
Every run photographed and, ideally, drawn.
Pressure tests and electrical checks recorded.
Certifier or designer has inspected the stage.
The next stage: insulation, airtightness and the air test.
Choosing the heating system comes first: see the heat pump guide and the solar PV guide.
First fix is the hidden work: cables, pipes, ducts and back boxes. Second fix is the visible work after plastering: sockets, switches, taps, radiators and light fittings.
A registered electrical contractor completes the work and provides a completion certificate. You also need this for the electricity connection and your records. Check the certification process with ESB Networks before work starts.
Yes. Ask for as-built drawings or photographs of every run before plasterboard. They help with later alterations, including drilling for a shelf or adding a socket.
Often, but they need to agree who goes first, because pipe runs and cable routes cross. Ask your builder to sequence the trades, with the insulation and airtightness team in the plan.
Last reviewed 20 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.
This guide is general information about self-building in Ireland, not financial, legal or insurance advice. Get advice that fits your own situation before you make decisions.