How long does planning permission last in Ireland?
Planning permission normally lasts five years from the grant. Check your expiry date, what unfinished work means and when to apply for an extension.
Stage 2: Design and planning permission
Who can object to a planning application, who can appeal the council's decision to An Coimisiún Pleanála, and how the four-week appeal deadline is calculated.
If you want to appeal a council planning decision, act within four weeks beginning on the decision date. If you are a neighbour, you generally need to have made a valid written submission to the council first.
An Coimisiún Pleanála (called “the Commission” below) decides planning appeals. The Planning and Development Act 2000 still calls it “the Board”. Check its current fees, oral-hearing rules and filing procedures at pleanala.ie before lodging anything. Judicial review in the High Court is a separate route requiring specialist advice.
The usual third-party appeal right depends on a valid, timely submission. Keep the council’s acknowledgement: it must accompany that appeal under section 127.
Section 37(1)(a) gives the right to:
Exceptions include prescribed bodies not properly notified and qualifying environmental organisations in cases with an environmental impact assessment report (section 37(4)). An adjoining landowner can apply for leave to appeal within the ordinary appeal period if council conditions materially change the proposal and materially affect enjoyment or value of their land (section 37(6)). This is not a general second chance for someone who missed the submission deadline. If leave is granted, the appeal must follow within two weeks of receiving the notification.
Your appeal must arrive within four weeks beginning on the day of the council’s decision (section 37(1)(d)). Count from that date, not when the letter reaches you. An appeal received late is invalid under section 37(3); there is no discretionary extension for an ordinary late appeal.
Two rules change the count. Days from 24 December to 1 January inclusive are not counted (section 251). If your last day falls on a weekend, public holiday or Commission office closure, your appeal can arrive on the next day the office is open (section 141(2)). Ask the Commission to confirm your final date, then lodge early with the fee and all required documents.
Check that your appeal contains everything required by section 127:
An incomplete appeal can be invalid. Do not assume you can send missing grounds later.
The Commission normally considers the application afresh, as though you had applied to it first (section 37(1)(b)). Its decision replaces the council’s. The whole proposal can be reconsidered and conditions can change in either direction. Section 139 allows the Commission, at its discretion, to deal more narrowly with a condition-only appeal where reconsidering the whole application is unwarranted. Special development-contribution appeal provisions also exist.
Section 37(2) lets the Commission grant permission even where the proposal materially contravenes the development plan. If the council refused on that basis, the Commission may only do so in limited cases, for example conflicting or unclear development plan objectives, or the pattern of development and permissions in the area.
If you want to be able to appeal later, make a written submission to the council during the application period. That is also the stage where the council can take your concern into account at the first decision.
Talk to neighbours before you lodge
A short conversation, and a design that deals with overlooking and access, is cheaper than a contested appeal. Keep the discussion focused on specific design concerns; agreement does not remove the need for permission.
For an ordinary one-off-house application, Article 29 of the Planning and Development Regulations provides a five-week written-submission period from the council’s receipt of the application. Give your name, correspondence address, application reference and clear planning grounds, such as overlooking, drainage or access. Use the council’s accepted submission route and keep proof of receipt.
The usual fee is €20, with exemptions and no second fee for a further submission on the same application: see planning costs. Late submissions and their fees must be returned. If the deadline falls on a day the council office is closed, it moves to the next open day (Article 29A), and 24 December to 1 January are not counted (section 251). These are national rules, so confirm your date with the council.
Significant further information may open another comment period under Article 35. Follow the published notice and council instructions; see the application stages. Keep comments about the proposal and avoid personal allegations.
For an ordinary non-commercial house application, the October 2026 appeal fees are:
| Who is appealing | Fee |
|---|---|
| Applicant: no retention | €220 |
| Applicant: includes retention | €660 |
| Applicant: special contribution condition only | €220 |
| Third party: council submission made | €220 |
| Observation on someone else’s appeal | €50 |
| Request for an oral hearing | €50 |
Commercial categories can cost more. Whether the application includes an environmental impact assessment report or a Natura impact statement also affects the fee category. Invited submissions on appeal documents sent to you by the Commission have no fee. Applying for leave to appeal costs €110, followed by €110 for the appeal if leave is granted. Reduced fees and exemptions apply to some organisations. Check the refund rules with the Commission before assuming you will get a fee back.
Because the decision is made afresh, an applicant appealing a condition can end up with a different set of conditions, not simply the one removed. Weigh that risk before appealing.
Allow for the council’s decision period, then the four weeks in which an appeal can be lodged. Only after those four weeks pass with no appeal does the council issue the final grant. An application for leave to appeal can also hold up the grant. Obtain the actual final permission and check pre-start conditions and building-control requirements before building. Before committing to a builder’s start date or a mortgage drawdown, confirm the planning evidence your solicitor and lender require. See mortgage drawdown.
If you hold a grant, see how long it lasts. For work built without one, see retention permission.
An Coimisiún Pleanála decides planning appeals. It replaced An Bord Pleanála and is called "the Board" in the Planning and Development Act 2000. Use the current name when searching for forms and fees.
Yes. As the applicant you can appeal to An Coimisiún Pleanála within four weeks of the council's decision, on payment of the appropriate fee.
Under section 37(1)(a), the right goes to the applicant and to those who made submissions or observations in writing on the application. A neighbour who made no submission to the council is generally outside that group. Section 37(6) also allows an adjoining landowner to seek leave to appeal in narrowly defined circumstances where conditions materially change the development and affect their land. Other statutory exceptions exist.
An ordinary late appeal is invalid under section 37(3). Christmas and office-closure rules affect the count, so confirm the deadline with the Commission.
A decision to grant is not the final permission. Wait for the final grant and satisfy pre-start conditions and building-control requirements before starting work.
Last reviewed 19 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.
This guide is general information about self-building in Ireland, not financial, legal or insurance advice. Get advice that fits your own situation before you make decisions.