Architect, architectural technologist or engineer: who do you need?
Choose a self-build designer and certifier in Ireland. Check registration and compare roles, inspections, fees and responsibilities before hiring.
What happens between the foundations and the first wall course in an Irish self-build: drainage, radon, damp-proofing, insulation and the slab pour.
The substructure is everything below the first floor level that you will never see again: the foundation walls, the drains that run under the house, the damp and radon protection, the insulation and the concrete slab. It is a short stage on site, often one to three weeks, but it hides more than any other. Below: what happens, what to ask for and what to photograph before the slab covers it.
The builder or the groundworkers do the work. Your designer specified the layers; your engineer has specified the concrete and any reinforcement. Your assigned certifier inspects at the points listed in the inspection plan. If your lender needs a stage inspection (often described as “foundations” or “ground floor level”), the lender’s inspector looks separately. See the assigned certifier and staged drawdown.
Radon is a radioactive gas that forms in rocks and soils and can enter a house through cracks in floors and gaps around pipes and cables. The Environmental Protection Agency (EPA) says it is a cause of lung cancer in Ireland, and its map shows High Radon Areas, where more than 10% of homes are predicted to exceed the national reference level. Radon barriers and sumps are far cheaper to build into a new slab than to add afterwards.
Ask your designer, before the slab:
After the house is finished, test for radon. A test is the only way to know your level. The EPA page explains how.
Water gets into a building where a barrier has a gap. The usual gaps are:
Photograph the membrane before the reinforcement and insulation go on. Photograph the DPC at a door threshold, which is the highest-risk point. Ask that nobody walks on the membrane in boots and that repairs are taped, not left.
The ground floor loses heat through its whole area. How much insulation and where it sits depends on the floor build-up in the drawings and the energy calculation behind the house’s Building Energy Rating (BER). Common options are rigid board under the slab, over the slab beneath a screed, or a mix. If you have underfloor heating, the insulation under the pipes matters twice: it reduces heat loss and makes the floor respond faster. Check:
See nZEB and Part L for the energy targets the floor helps to meet.
Once the slab is poured, a pipe in the wrong place needs a cutter. Before the pour check:
The slab is poured in one day where possible, with the concrete supplier’s docket kept. Concrete reaches design strength over weeks, but it can be built on much sooner. It should not dry too quickly in hot, windy weather or freeze in the first days; ask your builder how it will be protected. A power-floated finish is common when the slab is the finished floor surface. Where a screed will go over it, a rougher surface is fine.
A sand and cement screed needs far longer to dry than most people expect. The usual rule of thumb is about a day per millimetre of thickness up to 50 mm, and longer beyond that, but your screed supplier’s guidance for your product is the one to follow. Flooring that goes over it, particularly timber and vinyl, needs a moisture reading below the flooring manufacturer’s limit. See plastering, screed and drying out.
Lenders often tie a stage payment to the foundations or the ground floor slab. Confirm the stage name, who certifies it and what evidence they need before you tell your builder it can be invoiced. The stage payment planner shows the effect on your cash.
At this stage the site is open and the materials are valuable: reinforcement, insulation and fuel. Storm damage is rare in a slab, but water can flood excavations, and a pile of block or insulation can be stolen or blown away. Check that your contract works and liability cover is already in force and what its excesses are. If you are managing the build, look at insurance when you project manage, and when you are ready use the cover checker to see the types of cover that suit your build.
A radon barrier is a sealed membrane under the floor that stops radon gas from the ground entering the house. In some areas a sump, a small pit under the slab, lets a fan draw the gas out later if a test shows it is needed. Ask your designer which measures apply to your site.
The damp-proof course (DPC) is a layer in the walls that stops moisture rising or tracking sideways. The damp-proof membrane (DPM) is the layer under or in the floor. They must overlap and join so that water has no path round the edge.
Yes, but the pipes, insulation levels and screed thickness have to be designed together. Pressure test the pipes before the screed goes on and photograph the layout.
The floor is a large area of the house envelope. Part L of the Building Regulations sets energy performance limits for the whole building, and an uninsulated floor loses heat to the ground. Follow your designer's U-value calculation and the manufacturer's installation instructions.
Last reviewed 20 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.
This guide is general information about self-building in Ireland, not financial, legal or insurance advice. Get advice that fits your own situation before you make decisions.