The last stage of an Irish self-build: joinery, kitchen, bathrooms, fittings, painting and flooring, then commissioning, certificates and snagging.
Second fix is the part of the build you will see and touch every day: doors, stairs, kitchen, bathrooms, sockets, paint and floors. It is also the point where costs creep, delays come from late deliveries rather than slow work, and the paperwork needed to move in and to release the last payment comes together. Plan it as a sequence, and keep a list of what is still missing.
Make one list with item, supplier, order date, quoted lead time, delivery date and who receives it. Items that regularly hold up the end are:
Check each item on arrival for damage and compare it with the order before you accept it. A returned item takes weeks.
Take photographs of finished rooms before furniture goes in, so that later damage is easy to date.
Commissioning means someone qualified has started each system, measured how it performs and shown you how to use it. A boiler or heat pump that runs is not necessarily set up properly, and a ventilation unit with the wrong flow rates can leave the house damp. Do not accept “it’s working” as a handover.
Ask for these as the systems are finished and keep them in one folder:
| Item | What you need |
|---|---|
| Electrical installation | The completion certificate from the registered electrical contractor. See the ESB Networks certification process |
| Heating and hot water | Commissioning record, controls guide and servicing instructions |
| Gas or oil appliance | The installer’s certificate where fuel-fired appliances are fitted |
| Ventilation system | Commissioning record with measured flows |
| Wastewater system or sewer connection | Commissioning record and servicing details |
| Airtightness test | The test report |
| Completion certificate | Signed by the assigned certifier and builder, registered with the building control authority where statutory certification applies |
| Final BER | Issued after the assessor surveys the finished house |
| Warranties and manuals | Windows, roof, boiler or heat pump, wastewater unit, kitchen appliances |
| As-built drawings | Showing where services and drains actually run |
Where statutory certification applies, the completion certificate must be lodged and valid before the house is opened, occupied or used. Start the paperwork before the finishing work ends, because chasing a missing signature on the last day is the usual cause of a late move. See certificate of compliance on completion and BER certificate for a new home.
Do the inspection when the house is clean and well lit, not while the trades are still working in it. Snagging with a painter on a ladder in every room finds little and gets argued about.
Snag before the final payment, in writing, against the drawings and specification. Do a first pass yourself, then consider hiring a surveyor or engineer for a larger house. The full list of checks is in snagging your new house. Agree dates for repairs, and keep retention until the work is done, as your contract permits.
The pressure at the end of a build is high: the rental is ending, the bank is charging interest and the family wants to move. That is when people agree to move in before the paperwork is done. Resist it, and agree a realistic move date with the builder when the programme is set.
The last payments usually depend on completion evidence: the registered certificate, the final inspection by your lender’s inspector, and the end of the builder’s retention rules. Your builder’s final invoice and the lender’s final release may fall on different dates, so plan cash for the gap. See staged drawdown explained, mortgage interest during the build and the stage payment planner.
A finished house full of fittings is a theft target, and a leak or fire in an unoccupied new house is costly. Arrange the home policy to start when you take possession, and check that contract works cover continues until handover. Keep cover for the works until you have accepted the house in writing. See making a self-build insurance claim, structural defects cover and the cover checker.
Fitting internal doors, skirtings, architraves and stairs, kitchen and fitted furniture, sanitaryware and taps, light fittings, sockets and switches, radiators and controls, then painting and floor coverings.
It varies a great deal with the size of the house and how many trades work at once. A few months is common, and kitchen, joinery and flooring lead times can set the pace. Ask your builder for a programme and check it against delivery dates.
Not until the house has the certification the law and your lender require and it is safe to occupy. Under the Building Control Regulations the completion certificate must be lodged before the building is opened, occupied or used where statutory certification applies.
Before the last payment. Plan a first inspection when the builder says the house is complete, agree a written list and re-inspect after the repairs. See the snagging guide for what to check room by room.
Last reviewed 20 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.
This guide is general information about self-building in Ireland, not financial, legal or insurance advice. Get advice that fits your own situation before you make decisions.