How plastering, screeding and drying out work on an Irish self-build, how long to allow, how to dry the house safely, and what goes wrong with floors.
After first fix and insulation, the walls and floors are closed and finished. This stage adds a lot of water to the house in plaster and screed, and the house then needs time to dry before most finishes can go on. The common mistake is to treat drying as a gap in the programme to be squeezed. The cost of rushing it appears later as cracked plaster, lifting floors and mould.
The choice also changes the order of work. Wet plaster needs the windows in and the roof on, and the electrics and plumbing first fix finished. Drylining on studs can go on earlier but needs the airtightness layer completed before the boards cover it.
| Type | What it is | Watch for |
|---|---|---|
| Wet plaster | Layers of plaster applied directly to block or concrete | Water in the house, cracking in the first weeks, airtightness depends on the coat |
| Drylining | Plasterboard on dabs or studs, joints taped and skimmed | Gaps behind boards unless sealed, joint cracks, screws or dabs visible |
Either can be well done. Ask your plasterer which they are using and why. For an airtight house, ask where the airtightness layer is and how penetrations and board edges are sealed.
Check the finished surface in raking light: hold a torch parallel to the wall and see ripples, ridges and dips. Mark them with tape for repair while the plasterer is on site.
Screed is a layer of sand-cement or a flowing liquid screed laid over the floor structure. It levels the floor and covers underfloor heating pipes.
Plaster and screed hold a lot of water, and the house will not dry on its own if it is closed up. Drying needs two things at once: air movement to carry the moisture out, and warmth to help it evaporate.
If you use temporary heaters, avoid unflued gas or paraffin heaters that put water vapour and fumes into the house. They add moisture and can be a fire risk. Ask your builder what they plan to use.
A common source of conflict is that the plasterer finishes in a week while the drying takes a month. Put the drying period into the programme and the payment schedule so that nobody is pushed to lay floors early.
The plasterer and screeder work for the builder, or directly for you if you manage the build. The designer specifies the floor build-up, and the underfloor heating installer sets the heat-up schedule. The assigned certifier’s inspection plan may include a stage inspection before plastering, which is the last moment the hidden elements can be checked. If you are unsure whether a drying approach is safe for your build, ask the designer or the suppliers.
Most drying problems come from the programme, not the materials: a flooring date was fixed before anyone knew the screed thickness, or the heating was not connected until after the plaster went on. Work backwards from the flooring delivery to find when the screed needs to go down.
Plaster and screed may be separate payments in your builder’s schedule, and some lenders have an “internal finishes” or “plastered” stage. Check your offer. See staged drawdown explained and the stage payment planner.
Heaters, dehumidifiers and wet materials raise two risks: fire and water. Run temporary power safely, and check that the cover in place includes accidental damage and escape of water during the build. If you are heating an unoccupied house for weeks, someone should check it daily. See insurance when you project manage and the cover checker.
You have a written note of any cracks, with dates, so that a later movement can be compared with what was there on handover.
The flooring supplier has confirmed in writing the moisture level they accept, and your tester has recorded the reading against it.
Plaster dry and sound, screed cured and tested.
Moisture readings within the limits for the flooring you chose.
Heating and ventilation commissioned or running as the installer instructs.
The next stage: second fix and finishes.
A common rule of thumb is about one day per millimetre of thickness up to 50 mm, and longer beyond that, but drying depends on the product, the weather, heating and ventilation. Use your supplier's guidance and a moisture test, not the calendar.
Only when the screed supplier and underfloor heating installer say so, and in the way they say. A usual approach is to wait until the screed is cured, then raise the temperature gradually. Heating too soon or too hard can crack the screed.
Wet plaster is applied to masonry in layers and sets in place. Drylining uses plasterboard fixed to walls or studs, with the joints taped and skimmed. Drylining adds less water but must be sealed to be airtight.
Timber and many other floor coverings absorb moisture, and can cup, buckle or fail if laid on a damp screed. The flooring supplier states a maximum moisture level.