This is the stage when the house starts to look like a house. The walls rise from the slab to the point where the roof can start, including any upper floor. What you see on site depends on the method you chose: block, timber frame or insulated concrete formwork (ICF). The checks they share come first, then the differences. To choose between them, read timber frame, block or ICF.
Most Irish houses are built from concrete block, usually a cavity wall with an inner leaf that carries the load, a cavity with insulation, and an outer leaf that is rendered or clad.
A timber frame house is made as panels in a factory, delivered to the site and erected on the slab. It can go up in days, but the work around it needs planning.
The timber frame supplier’s own inspection or a certificate for the frame can support the certifier’s records, but it does not replace the certifier’s inspection of the site work.
ICF uses hollow insulated blocks stacked like toy bricks, reinforced and filled with concrete. It is a more specialist method.
Do not rely on memory. A wall of blockwork looks the same whether the cavity tray is in or not, and a certifier who visits on a day when the lintels are already built over can only record what is still visible.
Your assigned certifier will list wall stages in the inspection plan. Structural openings, lintel bearings, cavity details and first-floor connections are typical inspection points. If you use a timber frame, ask whether the plan includes the factory production or whether it relies on the supplier’s documents. See the assigned certifier and building regulations.
Your engineer should confirm any change you ask for on site. Moving a window or widening an opening affects lintels, loads and heat loss.
With a tape in each picture, record:
Check dimensions as you go: levels, door and window sizes against the order, and the thickness of the cavity.
Most wall defects are cheap to correct while the wall is one course high and expensive once the roof is on. Walk the site yourself once a week and compare what you see with the drawings, even if you are not an expert. Questions are free.
Wall stages are also where variations pile up: a bigger window, a moved door, an extra steel beam. Ask for a price in writing before the change is built, and give the certifier the revised drawing so that the completion certificate matches what exists.
This is often a lender’s stage, called “wall plate”, “first floor” or “walls up”. Confirm which one applies and whether the lender’s inspector wants to see it before the roof starts. Your builder’s payment schedule may tie payments to different points than the lender’s, so keep the stage payment planner up to date.
Open walls without a roof are exposed. A storm can damage unprotected frames, scaffolding and stored materials. Scaffolding creates a falling and theft risk, and a stranger on site can be injured. Make sure your contract works and public liability cover is current, and check whether the cover includes damage by weather before the roof is on. See insurance when you project manage and the cover checker.
The wall plate is the timber that sits along the top of the external walls and carries the roof. Wall plate level means the walls are built to the point where the roof structure can start.
For a typical house, block walls often take four to eight weeks depending on size, weather and the number of bricklayers. A timber frame is manufactured off site and can be erected in days once it is delivered. Allow for the lead time on the frame, which can be several months from order.
Not alone. Ask your designer or certifier to inspect and record them, and take your own photographs as well. They cover the openings and the transition between floors, which are common leak points.
Block and concrete can tolerate rain better than timber and insulation, but standing water, saturated insulation and wet mortar in cold weather cause problems. Protect the tops of walls and keep timber frame components covered until the roof is on.
Last reviewed 20 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.