Site preparation and service connections for an Irish self-build: access, water, electricity, wastewater and broadband, and what to apply for early.
Apply for electricity and water connections as soon as you have planning permission, and agree access, drainage and temporary services before site work starts. Budget for each connection separately from the house.
When you apply, the provider sends a connection offer, which sets the cost and conditions for your site. Check current charges and lead times before committing money, especially if you need a long cable or pipe run, a road crossing or work on someone else’s land.
| Service | Who to contact and when |
|---|---|
| Electricity | ESB Networks, when planning is granted |
| Mains water | Uisce Éireann, when planning is granted |
| Mains sewer | Uisce Éireann, with your water application |
| Private well | A driller and water-supply designer, alongside wastewater design |
| Wastewater system | Your designer and installer, before construction |
| Broadband | Retail providers or National Broadband Ireland, at design stage |
For electricity, allow about €3,600 for a standard connection or about €4,900 for an enhanced 16 kVA supply within the standard terms. Capacity is measured in kilovolt-amperes (kVA); ask your electrical contractor which supply you need. Quotation targets are 7–15 working days, followed by a connection target of about 60 working days subject to the conditions below.
The standard mains-water charge is about €2,270 for a 25 mm pipe covering up to 10 m. Ask Uisce Éireann for your water and sewer costs and programme. Sewer charges, well costs and installation times depend on the site. Get a wastewater quote using the wastewater guide; check retail installation and subscription terms for broadband. Do not assume a well grant is available for a new build.
Standard charges cover defined work for a single house. Anything outside those limits is quoted separately, so a long run from the road can cost far more.
Your planning conditions may specify the entrance, sight lines, drainage, boundary treatment and landscaping. Read them before you order any work. Check the approved entrance drawings and the applicable road standards with your designer. Visibility requirements depend on the road and the permission; do not adopt a distance from another site. A hedge or boundary outside your control may prevent the approved entrance from being delivered.
The visibility splay is the area that must stay clear so drivers can see along the road from your entrance. Do not assume an informal arrangement with a neighbour gives you the rights you need over that land. Ask your solicitor to confirm you control all the land the condition needs.
Typical early works are, in order:
Agree who supplies each item with your builder, as covered in the contract, because “site clearance” and “temporary services” are common gaps between a quote and the final bill.
If you plan to live on site during the build, the temporary connection and unit have their own rules: see living on site while you build.
Apply to ESB Networks for a new domestic electricity connection. For a single house on a new site, work through these steps:
The published standard charge for a single house is €3,602 for a standard connection and €4,877 for an enhanced 16 kVA connection. If your site is a long way from the network, or needs poles or underground cable beyond the standard, the cost is quoted separately. Ask for the quote early: it is the best way to learn whether the site is cheap or expensive to serve before you are committed to it.
Allow time in your programme since lead times can be long. Ask ESB Networks and your electrical contractor how temporary site power will be provided; do not assume the permanent connection quote includes it.
Where there is no public sewer, you will need a treatment system designed from a site suitability assessment. See wastewater treatment systems. Position the system, the well and the house together at design stage: the distances between them are set by the code, and moving one can force the others to move.
Use the National Broadband Ireland (NBI) map to check your Eircode against the intervention area and its estimated dates. Those dates may change. If your new address is missing or outside the mapped area, contact NBI and retail providers with the location and Eircode. Obtain confirmation of availability and installation requirements before relying on a connection date.
Agree duct routes and specifications with each provider and your designers while planning trenches. Coordinate separation, access and safe installation; spare ducts are useful only if their route and specification suit the intended service. Check availability directly if considering gas.
List each connection with an estimate and a request date. Add them to your budget as separate lines, with a contingency on the long-run and rural items, and include them in the stages plan so nothing delays your move-in. Request electricity and water quotes as soon as you have planning, even if payment will be later. Check each offer’s conditions and validity before relying on its price or dates.
For each service, record who applies, who pays, who installs ducts or pipes and what must be ready before connection. Ask the builder to confirm which of these tasks are in the contract. Update the list when the provider issues its offer, so a missing certificate, trench or supplier account does not hold up the connection.
For the water choice in detail, see water supply for a one-off house.
ESB Networks handles new connection applications for domestic premises. Apply as soon as you have planning permission, and check the current process with ESB Networks.
In many places Uisce Éireann provides connections. Where mains water is not available you may need a well or group scheme.
You will need an on-site wastewater treatment system designed for your site after a site suitability assessment.
Often not. Check what the contract includes and budget connection charges separately.
Last reviewed 19 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.
This guide is general information about self-building in Ireland, not financial, legal or insurance advice. Get advice that fits your own situation before you make decisions.