Stage 7: Completion and handover
How to snag a self-build in Ireland before final payment: what to check room by room, how to record defects, and retention and certificates.
Arrange snagging before handover and before final payment falls due. A written list makes it easier to agree repairs while the builder is still on site. Paying or moving in does not automatically remove your rights over defective work. Agree repair dates and follow the payment and notice procedures in your contract. Your contract and specification help establish what work is due; ask your certifier about compliance and a solicitor about disputed payment.
A snag is anything that is unfinished, damaged, or does not match the drawings and specification. The next step depends on what you find:
| Problem | What to do |
|---|---|
| Finish or workmanship: missed paint, a sticking window or cracked tile | Check against the specification and put it on the builder’s snag list. Agree repairs before final payment falls due, following the contract |
| Possible non-compliance: missing insulation, incorrect fire stopping or missing ventilation | Ask your designer or certifier to assess it against the regulations. Give written notice, arrange repairs and re-inspection, and resolve it before certification |
| Possible structural or hidden defect: a moving wall or persistent damp from a wall or roof detail | Ask an engineer for a report. Then pursue the builder, applicable structural defects cover or legal advice as appropriate |
Agree with the builder, before the inspection and ideally in the contract, what counts as a defect as opposed to a small snag: “a defect is anything not in accordance with the drawings, specification and the contract standard of workmanship”. A request to change an agreed finish may be a variation: agree its price and effect on the programme before authorising it.
Do not wait for the builder to say it is finished. Snagging works best in three passes:
Plan a further review during the contractual defects period, including after the first heating season where timing allows. Report new damp, cracks or system faults promptly rather than waiting for that review.
Gather the drawings, specification, schedule of finishes, the Building Energy Rating (BER) assessment, any list of changes agreed on site and your certifier’s inspection records. Inspect in daylight, on a dry day if possible and then again in or just after rain. Allow enough time for the house and the agreed inspection scope.
Bring a torch, a spirit level or a long straight edge, a phone for photos, masking tape or small stickers to mark each defect on the wall, a tape measure, and a notebook or spreadsheet. If a professional proposes thermal imaging, ask what conditions are needed and what the survey can establish.
Keep checks to areas you can safely reach. Do not open electrical equipment, climb onto roofs or enter an unsafe attic. A visual snag list and a socket tester cannot certify electrical or structural safety. Ask the relevant professional to investigate concerns.
List each item with room, location, description, photo and a target date. A spreadsheet with a row per item works well: columns for room, description, photo file name, date raised, date promised, date fixed and signed off. Number the items so the builder can answer by number.
Send one consolidated list, by email, keep a dated copy, and ask the builder to confirm receipt and a date. A single list helps you track agreed work and dates. Send any new problems as a second numbered list; keep the original so you can see what has been resolved.
The paperwork is as important as the finishes, because you will need it to sell, remortgage, or insure the house.
| Document | Why it matters |
|---|---|
| Certificate of Compliance on Completion | For works within statutory certification, get the signed certificate and confirm registration before occupation. See the paragraph on completion certification below |
| Final BER certificate | Replace the provisional rating with a final rating based on the finished house. You need a BER to sell or let |
| Electrical certificate | Obtain from the registered electrical contractor; confirm any lender or insurer document requirements |
| Gas or oil installation certificate | Obtain the applicable installation and commissioning records if you have a fuel-fired appliance |
| Heat pump, solar and ventilation commissioning records | Evidence for operation, maintenance and the BER assessment; check any applicable grant requirements |
| Airtightness test result | Part of the BER evidence |
| Manufacturer warranties and manuals | Windows, boiler or heat pump, roof tiles, wastewater unit |
| As-built drawings | Services and drainage routes, valuable later for extensions |
| Structural defects cover documents | If your lender or buyer requires it, confirm eligibility and inspection requirements early rather than assuming it can be bought at completion |
| Planning conditions compliance | Evidence that conditions were met, such as landscaping, boundary or wastewater requirements |
Where statutory completion certification applies, your assigned certifier and builder sign the certificate and upload it through the Building Control Management System (BCMS). The authority checks that it uses the prescribed form, is signed and complete, and enters it on the statutory register. Confirm registration before occupation or use. A single dwelling whose owner lodged a valid opt-out of statutory certification (possible for eligible homes since September 2015) follows a different certification route, while still having to comply with Building Regulations. Agree the documents needed for occupation, final drawdown and any future sale with your professionals and lender.
A new dwelling’s provisional BER is based on drawings and is valid for a maximum of two years. Replace it with a final BER based on a survey of the finished house.
Check the final payment date, certification requirements and notice procedure before handover. An outstanding snag does not automatically allow you to withhold the entire balance. The contractual tools to agree at the outset include:
Hypothetical example: on a contract of €300,000 with a 5% retention, €15,000 is held. If the contract releases half at practical completion and half after six months, you would release €7,500 at completion once the snag list is cleared, and keep €7,500 until the end of the defects period. If your contract has no retention clause, you have much less leverage. That is a reason to settle this when you choose the contract rather than at the end.
Retention and a legal right to withhold payment are different. For service contracts within Part 4 of the Consumer Rights Act 2022, section 91 provides a withholding right and requires a statement to the trader. For defective services, the amount must be proportionate to the reduction in value of what was supplied. Ask your solicitor whether it covers your building contract before withholding or deducting money; repair cost alone is not an automatic entitlement. If you are on a project-managed build, the same principle applies to each trade contract.
Do not treat the contractual defects period as the deadline for every legal claim, or assume that discovering a defect starts a fresh period. The applicable time limit and when it starts depend on the claim and facts. Get legal advice promptly on a serious or unresolved defect; a snag email or ongoing negotiations should not be assumed to preserve your right to sue.
Keep a running list of issues over the first year, particularly settlement cracks, heating and ventilation performance, and damp after the first winter. Report each one in writing. Before completion or occupation, agree the insurance transition in writing with your broker or insurer. Confirm the construction policy’s end trigger and that replacement cover accepts the actual occupancy and any outstanding work.
Snagging is a systematic inspection to record defects and unfinished work for the builder to address. Repairs and payment follow the contract and applicable law.
Consider a building surveyor or engineer for a large or complex house. Agree an inspection against the drawings and specification. You can also do your own first pass and give the inspector your list of concerns.
A percentage of the contract price held back, as agreed in the contract, until defects are fixed. Check the figure and release conditions in your own contract.
Notify the builder in writing and ask your designer or surveyor to assess disputed items. Take legal advice on remedies and payment; a structural warranty only helps with defects within its terms.
Last reviewed 19 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.
This guide is general information about self-building in Ireland, not financial, legal or insurance advice. Get advice that fits your own situation before you make decisions.