Getting the roof on and the windows in is the biggest milestone on site. It turns an open frame into a shell that rain cannot reach. After that the inside can dry and the interior trades can begin. It is also the stage where lenders, insurers and your own programme all ask the same question: is the house weathertight yet?
The sequence of 7 and 8 varies. Some builders fit windows before the roof covering is finished, with temporary cover.
Agree before the roof goes on who is responsible if it rains while the structure is open. In a main-contractor build the contractor normally carries that risk under the contract. If you are managing trades yourself, it is yours, and you should ask your insurer how that is treated.
The roof is often a separate trade from the walls. The truss supplier designs and delivers the trusses, a roofer fits the covering, and a window supplier fits the openings. Your designer and engineer specify the structure, and your assigned certifier’s inspection plan should include the roof structure before the covering. The lender’s inspector may separately confirm the roof stage. See the assigned certifier.
If the trusses were designed by the supplier, ask for their design drawings and any certificate, and confirm that the engineer and certifier accept them.
Get a record of each of these before the covering hides it:
Take photographs of the underlay and battens, and of any area that will be hidden by fascia or flashings.
Think about security as well as weather. Until the external doors are fitted with working locks, anyone can walk in, so most builders fit temporary doors or board up the openings and hand the keys to one person.
Windows and doors are a major part of the thermal envelope and the security of the house. Check:
Window orders have lead times, often several weeks and sometimes longer. Order from the final dimensions, and measure on site if you changed openings.
There is a practical reason for this too. Once the shell is closed, the inside can dry and the interior trades can start without fear of water damage, so the programme speeds up. Work out how many weeks you have between weathertight and plastering, because that is when delays in joinery, windows or first fix show.
A weathertight shell is a recognised milestone. Many lenders have a stage for it, and an inspector may need to see the roof. An insurer may ask whether the roof is complete when you arrange cover, because an open house is a different risk from a closed one. Tell your insurer or broker when the shell is complete, in case your cover or its conditions change. Look at your contract works policy for exclusions around storm damage or theft of unfixed materials, and keep records. See what lenders require.
Make sure cover is in place for the works, the materials on site and your liability to others, and that it names who is insured. Use the cover checker to see which types suit how you are building.
If your lender pays a stage at roof level, check what the lender’s inspector needs and whether the payment arrives before the builder’s invoice. See staged drawdown explained and the stage payment planner.
You know the date the shell was closed, in case your insurer or lender asks for it.
Any storm or leak damage found while the roof was open has been recorded and either repaired or listed.
The roof, windows and external doors are fitted and secure.
Inspection records and photographs are saved.
The lender’s stage evidence is submitted.
The next stage is first fix.
It means the roof is covered and the windows and external doors are fitted and closed, so rain and wind cannot get in. Interior work such as first fix and insulation depends on this milestone.
Most Irish houses use prefabricated timber trusses or cut-timber rafters on the wall plate, with battens and a breathable underlay under slates or tiles. A designer or engineer specifies the sizes and fixings.
Usually after the structure is up and the roof is on, but the order depends on the programme. Check with your builder when the windows arrive and who protects openings in the meantime.
Many stage-payment schedules include a roof or weathertight stage, and the lender may send an inspector to confirm it. Check your own offer for the stage names and the evidence needed before the roof is complete.
Last reviewed 20 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.
This guide is general information about self-building in Ireland, not financial, legal or insurance advice. Get advice that fits your own situation before you make decisions.