Windows and external doors are one of the biggest single purchases in a one-off house, and one of the easiest to get wrong. The frame and glass you choose affect your energy rating, the airtightness test, your security and the date the house is weathertight. Decide the specification before the roof goes on and the order shortly after, so the units are ready when the shell is.
Part L (the energy rule in the Building Regulations) sets a maximum U-value of 1.4 W/m²K for windows, doors and rooflights in a new dwelling. The U-value measures heat lost through the whole unit, frame included. Lower is better.
You do not meet Part L window by window. Your designer’s energy calculation (DEAP) adds up the whole house, so a weaker window can be offset elsewhere, but not past the 1.4 limit. The guidance’s own worked example for a typical 126 m² semi-detached house that complies uses triple-glazed, low-E, argon-filled windows in PVC frames at 0.9 W/m²K, with openings equal to 25% of the floor area. That is an example of one way to comply, not a specification for your house.
Ask your designer for the U-value and the solar transmittance (g-value) they assumed in the calculation, and write both into the order. Windows that are cheaper but worse than the assumed figure can put the BER or compliance at risk. See Part L and nZEB requirements.
Triple glazing costs more. Windows suppliers’ guides put the extra at roughly 30% to 50% over double glazing, and the installed price list below shows the gap by frame. What you get is a lower U-value, warmer glass surfaces and less condensation. It also makes it easier to meet the 1.4 limit when you want large glazed areas, because big windows lose more heat.
Ask your designer to run the calculation both ways. If double glazing passes with room to spare on a house with modest glazing, you may not need triple. If you want large south-facing openings or a Passive House standard, triple is likely to be needed. See Passive House or nZEB.
| Frame and glazing | Installed, per m² |
|---|---|
| uPVC, double | €450 to €750 |
| uPVC, triple | €650 to €950 |
| Timber, double | €700 to €1,100 |
| Timber, triple | €900 to €1,400 |
| Aluminium, triple | €900 to €1,400 |
| Alu-clad timber, triple | €1,000 to €1,500 |
These are indicative installed prices per m² of window, not quotations. Prices quoted by some window makers are much lower, around €450 to €620 per m² for triple-glazed uPVC, aluminium or timber, often without saying whether VAT or fitting is included. Expect a wide spread: get at least three written quotes, ask whether each includes VAT, fitting, delivery and the airtightness tapes, and compare the same specification.
A 150 m² house has about 25 to 35 m² of windows. At 30 m², triple-glazed uPVC works out at about €19,500 to €28,500 on those ranges, and alu-clad at €30,000 to €45,000. Add external doors, sliding or bifold doors and rooflights, which are priced separately.
How the frames differ:
Sizes drawn on plans are not always the sizes built. Blockwork, timber frame and insulation tolerances all shift an opening by a few millimetres, and a unit that is too big does not go in. Many self-builders confirm the order against the built openings once the walls are up, and some suppliers supply temporary formers to build to. Ask your supplier which they use, and who takes responsibility for the dimensions.
Lead times vary from a few weeks to several months, and they change with the season and the supplier’s order book. Put the delivery date in the order confirmation, and work back from the date you want the house weathertight. The roof and weathertight shell guide covers where windows sit in the sequence, and the timeline planner lets you test a late delivery.
Before you place the order, check that it states:
Suppliers usually ask for a deposit when you order, with the balance before delivery or fitting. Your lender releases money against the building’s stages, not against a supplier’s invoice, so a large deposit in month three can open a cash gap. Add it to the stage payment planner as an upfront cost, and see staged drawdown.
Keep the deposit as small as you can negotiate. Ask what happens to it if the supplier cannot deliver, and pay by a method that leaves a record. If the supplier stops trading, a deposit may be a claim among many others.
How the frame is fixed and sealed matters as much as how good it is. Ask who fits the units and who is responsible for the seal between frame and wall. In an airtight build that is usually tapes or membranes applied inside and outside, so the fitter needs the design details first. A poor seal will show up at the airtightness test. See insulation and the airtightness test.
Check:
Window installation falls under your build’s inspection plan. Ask your assigned certifier what they inspect and when, and keep the delivery notes, specifications and photographs for the completion certificates. The statutory framework is in the Building Control Regulations as amended in 2014. See commencement notice and BCAR.
Windows and doors spend time in places your insurance may not reach:
Tell your broker the delivery date and the value of the units, and ask whether the sum insured reflects them. Use What insurance do I need? for a checklist that matches your stage, and see self-build insurance.
Part L sets a maximum U-value of 1.4 W/m²K for windows, doors and rooflights in a new dwelling. The guidance's own worked example for a house that complies uses triple-glazed windows at 0.9 W/m²K. Your designer's energy calculation decides what your house needs, but triple glazing is the common choice.
Any well-made frame can last decades. They differ in upkeep: timber needs its coating renewed, uPVC and aluminium need cleaning, and alu-clad puts an aluminium shell on a timber frame so the outside needs little attention. Ask each supplier for the warranty terms on frame, coating and glass separately.
Settle the specification before the roof goes on, then confirm sizes against the built openings and give the supplier the order. Ask for the manufacturing and delivery time in writing and plan the programme around it.
Not automatically. Works cover usually applies to materials on site, but units held at a supplier's premises may not be covered until delivered. Check the wording and tell your broker when delivery is planned.