Water supply for a one-off house: mains, group scheme or well
Compare an Uisce Éireann connection, a group water scheme and a private well for a rural self-build. Costs, testing and what lenders ask for.
How solar panels help a new house meet the Part L renewable energy ratio. When you need them, how many kWp, what they cost and the planning exemption.
Ask your designer for the DEAP result before you decide how many solar panels to buy. New houses must reach a Renewable Energy Ratio (RER) of at least 20%, and photovoltaic (PV) panels are the most common way for a one-off house to close the gap.
The nZEB guide sets out the three whole-house targets in the Part L guidance for dwellings. The RER is the share of the house’s primary energy that comes from renewable sources, and it must be at least 20%. The regulations count energy produced on site or nearby: solar PV, solar thermal and the renewable share of heat from a heat pump all count.
That means the RER is a result, not a product. Your designer enters the fabric, the heating system and any panels into the Dwelling Energy Assessment Procedure (DEAP) and reads the result. If the RER is below 20%, they add renewables or change the heating until it passes.
It depends on your heating system:
Ask your designer for the RER with and without panels. If the house passes comfortably without them, you can choose panels for their running-cost benefit instead of compliance. If it only passes with them, treat them as part of the build, with the cost in the budget and the array on the drawings.
Panels are sized in kilowatts peak (kWp), the output of the array in standard test conditions. One Irish comparison site, which is run to generate installer leads, reports that most Irish homes use 8 to 12 panels, which is 3.5 to 5.3 kWp, and that 10 panels (4.4 kWp) is the usual choice. It reports yields of about 817 to 965 kWh per kWp a year depending on the county, so a 4 kWp system generates roughly 3,270 to 3,860 kWh a year.
Those are retrofit and typical-home figures. For a new build, your designer fixes the size from three things:
A bigger array costs less per kWp but stops being useful if you cannot use or export the power.
The same comparison site publishes these prices for 2026, based on quotes from SEAI-registered installers, before any grant:
| System | Panels | Typical price |
|---|---|---|
| 3.5 kWp | 8 | €7,500 to €8,500 |
| 4.4 kWp | 10 | €8,300 to €9,000 |
| 5.3 kWp | 12 | €9,200 to €9,900 |
| 6.2 kWp | 14 | €10,500 to €11,500 |
Source checked 21 October 2026. Prices vary with the installer, the equipment and the complexity of the roof. A battery or a complicated roof adds to the price. Get itemised quotes that name the panels, the inverter, the mounting system and the commissioning.
Ask each quote to state the VAT rate it assumes. Do not assume a grant is deducted: see below.
The SEAI solar electricity grant requires a house built and occupied before 2025, and approval before work starts. A new house fails the age test, so budget the full price. Our SEAI grants guide explains the rules and the order of steps for an existing house.
Most roof-mounted panels on a house do not. The exemption in the Planning and Development Regulations, as amended in October 2022, applies where:
Ground-mounted panels at a house are exempt up to 25 m² and 2.5 m high, if they are not in front of the house and you keep at least 25 m² of open space at the back or side. Panels fixed to a wall, and panels on protected structures, always need planning permission. In a conservation area, check the frontage rules.
If your house is under planning permission, putting the panels on the drawings now avoids questions at completion. Ask your architect to show them, and confirm with the council if the layout is unusual.
Panels need an inverter and a connection agreement with the electricity network, which your installer normally arranges. Ask your electrician to run the cable routes at first fix, so you do not open finished walls later. Ask your supplier about the export tariff when you move in. Tariffs change often, so do not rely on a figure quoted years before you complete.
A battery stores daytime power for the evening. It adds a four-figure sum to the price and is not needed to meet Part L, so treat it as an optional extra and price it separately. If you plan to charge an electric car at home, the new-build guidance also expects the electrical installation to allow for a charge point. Tell your electrician now, so the cable and the consumer unit are sized for it. A car charging in daylight is also one of the best uses of the panels’ output.
Tell your insurer about the panels before they go on. They are part of the roof and add to the rebuild cost. Add them to the sum insured at completion and to your lender’s schedule if it asks for one.
A solar comparison site explains panels, prices and payback well, but it does not cover how a new house meets Part L, what the RER is, or why a design may need panels at all. This guide adds the compliance route, the DEAP link to the heating choice, and the order in which decisions have to be made on a new build. Use the comparison site for installer prices and county yields, and your designer for the number of panels your house needs.
Before the first day on site, check the cover you need: your site and contract works policy should be in place on the day work starts. See what cover you need.
Not by name. Part L requires a Renewable Energy Ratio of at least 20%. A heat pump can supply a large part of it. Panels are the most common way to cover any shortfall, and your designer's DEAP result tells you whether you need them.
There is no fixed size. Typical Irish homes use 3.5 to 5.3 kWp, which is 8 to 12 panels. Your designer sizes the array to the DEAP result and the roof area.
No. The house must be built and occupied before 2025. See the SEAI grants guide.
Most roof-mounted panels on a house are exempt under the Planning and Development Regulations. Wall-mounted panels, protected structures and some conservation-area frontages are not. Ask your council or architect about your site.
Panels reduce the electricity you buy and can earn export payments. Payback depends on how much you use in daylight hours, your tariff and the system cost, so ask for a worked estimate from your installer.
Last reviewed 21 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.
This guide is general information about self-building in Ireland, not financial, legal or insurance advice. Get advice that fits your own situation before you make decisions.