What is retention (holdback) in a building contract?

Retention is an agreed share of the contract price, or of each payment, that you hold back from the builder until the work is finished and defects are put right.

Last reviewed 3 sources

Quick answer

Where it comes from
Your building contract. If it has no retention clause you have much less leverage.
Typical shape
A percentage of each payment or of the total, with a cap, released partly at practical completion and the rest after a defects period.
Example
On a €300,000 contract, 5% retention is €15,000. If half is released at completion, €7,500 remains until the defects period ends.
Different from
A statutory right to withhold payment for defective services, which has its own rules.

How it works in Ireland

Retention is a contract term, not a right you have by default. Standard forms for building contracts include it, and the contract should state the rate, the cap, when each part is released and the defects period. Follow those terms, because you cannot invent a new release condition at the end of the job.

A common pattern deducts a percentage from each stage payment up to a cap. Half is released at practical completion, once the snag list is cleared, and the rest at the end of the defects period, often six or twelve months. The figures are illustrative and vary by contract. Record them, and diary the release dates.

Retention is not the same as your lender’s holdback. A lender holding money back does not by itself entitle you to withhold from your builder, and the builder’s contract controls the builder’s payments. Read the lender’s staged drawdown schedule alongside the contract’s so the two line up.

Separately, for defective services within Part 4 of the Consumer Rights Act 2022, section 91 provides a right to withhold payment and requires a statement to the trader. The amount must be proportionate to the reduction in value of what was supplied. Ask your solicitor whether it covers your contract before you rely on it.

Retention is also a protection if a builder fails. Money you have not paid is money you have not lost. See what to do if your builder goes bust.

A common mistake

Withholding the whole final payment because of a long snag list. A snag list does not automatically entitle you to hold every remaining payment. Withhold only what the contract or the law allows, in writing, with the defects listed. Get advice before holding a disputed sum.

The full guide

This page defines the term. The guide below covers what to do about it.

Sources

Last reviewed 23 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.

  1. Retention guidance noteSociety of Chartered Surveyors Ireland
  2. Consumer Rights Act 2022Irish Statute Book
  3. Construction Contracts Adjudication ServiceDepartment of Enterprise, Trade and Employment

All money terms and the rest of the glossary