Stage 5: Notify Building Control
What to do when your builder stops work on your self-build in Ireland: secure the site, value the work, close the insurance gap, restart and recover money.
If your builder stops turning up, act on three things the same week: secure the site, get the work done so far recorded and valued, and find out whether the part-built house is still insured. Then take legal advice before you end the contract or bring anyone else in. Most of the money lost in these cases is lost through paying ahead of the work, so the best protection is set up before you sign.
A builder can walk off the job: a dispute about money or variations, a better-paying contract elsewhere, illness or simply overcommitment. The business still exists and you can still hold it to the contract.
Or the builder’s business can fail. A company may go into liquidation, receivership or examinership; a sole trader may stop trading or become insolvent. Once a liquidator or receiver is confirmed as appointed, you deal with them rather than the builder. In examinership an examiner is trying to rescue the company, so the aim is different, and a sole trader who stops work has no such appointee. Your chances of recovering money depend on what is left.
Early on you may not know which it is. A builder who has stopped answering the phone may be in financial trouble. Search the company on the Companies Registration Office (CRO) register: check its status and its filings for any appointment of a liquidator, receiver or examiner. A receiver’s appointment can be filed while the company’s status still reads Normal, so look at the filing details and not only the status.
Leave the builder’s plant, scaffolding and stacked materials where they are for now. Materials not yet built into the house may belong to an unpaid supplier under their terms of sale, or form part of what a liquidator collects. Record them, and ask your solicitor before you move, use or sell any of them.
This is the risk people miss. If your builder arranged the contract works and public liability cover, as many main contractors do, that cover was arranged for their contract and their operations. Once they leave, it may stop applying to your site, or end altogether if the business fails. The part-built house, any materials you have paid for and your liability to visitors may then have no cover.
Do this the same week:
A part-built house with no roof, or with open window openings, is exposed to weather and theft. Agree temporary weatherproofing with your engineer and tell your insurer what has been done.
Then use What cover do I need? to make a checklist for the build as it is now, with the option to ask for an insurance callback.
Tell your lender as soon as work stops. A self-build mortgage is released in stages, each usually against a certificate from your architect or engineer, and the lender will want to know how the house will be finished within the approved budget. Expect to show the valuation of work done, the price for finishing it and evidence of insurance. A higher price to finish the house is a common gap after a builder failure. Our guides to staged drawdown and funding a gap in the build cover what lenders ask for and where the shortfall can come from.
You can retender the remaining work to a new main contractor, or finish it yourself by hiring trades. A new builder will price the risk of taking over someone else’s work, including defects they didn’t create, so expect a higher rate than the original tender for the same scope. Give them the valuation, photos and drawings so they price the real position. The project manage or hire a main contractor guide covers the trade-offs.
If you change the builder after submitting your commencement notice, you must notify the building control authority within 14 days, with the new notice of assignment of the builder. On the opt-in route, send the builder’s undertaking with it, and if your assigned certifier also changes, the certifier’s notice and undertaking too. If you opted out of statutory certification (S.I. 365/2015, Article 6), the builder’s undertaking and assigned-certifier documents do not apply, but you still assign the builder, so check with your building control authority what the update needs. Ask your assigned certifier to inspect and record the work done before the new builder covers anything up. See the commencement notice guide and assigned certifier explained.
As the client, you must appoint a project supervisor for the construction stage. Often that was the builder. If so, appoint a replacement in writing before anyone restarts work on site. The Health and Safety Authority’s guidance for home owners explains the client’s duties.
What you can recover depends on what you paid for and whether the business still exists.
Adjudication under the Construction Contracts Act 2013 is a fast route for payment disputes, but it excludes a contract for a house of no more than 200 square metres that one of the parties lives in or intends to live in. Many self-builds fall inside that exclusion. Your own contract may still have a dispute procedure, such as conciliation or arbitration.
You can’t make a builder failure impossible, but you can limit how much it costs you.
This example is illustrative. Aoife’s builder stops work after the walls reach wall plate. She has paid €140,000 of a €320,000 contract, including a €15,000 deposit by bank transfer. Her engineer values the completed work at €128,000, so she has paid €12,000 more than the work is worth, and the work left is worth €192,000 at the contract rates. A new builder prices it at €205,000, €13,000 more.
Finishing the house now costs €345,000 (€140,000 paid plus €205,000) against the original €320,000: a €25,000 gap, made up of the €12,000 overpayment and the €13,000 higher price, before any legal costs. The builder’s company goes into liquidation, so she lodges a claim as an unsecured creditor, knowing she may not get much back. She tells her lender and her insurer the same week, arranges site cover and temporary weatherproofing, and notifies the council within 14 days of appointing the new builder. Had the deposit been paid by card, she could have asked about a chargeback. Had every payment followed a certified stage, she would not have been €12,000 ahead of the work.
Buying someone else’s part-built house? Use the unfinished-house purchase checks before committing to the sale.
Don't assume so. If the builder held the contract works policy, ask the insurer or broker in writing whether cover continues for the part-built house and materials, and for how long. Arrange your own cover before anyone else works on the site.
Not without advice. Materials not yet built into the house may belong to an unpaid supplier or, in a liquidation, be claimed by the liquidator. Record what is there and ask your solicitor before moving or using any of it.
Possibly some of it. A consumer owed money is usually an unsecured creditor, ranking behind secured and preferential creditors such as banks, Revenue and employees. Write to the liquidator with your claim and evidence.
Usually not, but if you change the builder after submitting the commencement notice you must notify the building control authority within 14 days, with the new notice of assignment of the builder. Owners on the opt-in route also send the builder's undertaking; owners who opted out of statutory certification should check with their building control authority what the update needs.
Search the company on the Companies Registration Office (CRO) register, ask for current insurance certificates, check registration on the Voluntary Construction Register, and speak to recent clients. Keep payments tied to certified stages.
Last reviewed 21 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.
This guide is general information about self-building in Ireland, not financial, legal or insurance advice. Get advice that fits your own situation before you make decisions.