What is a defects liability period?
The defects liability period is a period set by the building contract, after practical completion, during which the builder must return to correct defects you notify, and at the end of which the remaining retention is normally released.
Quick answer
- Set by
- Your building contract. Check the length and the notice procedure.
- Starts
- Usually at practical completion.
- Linked to
- The second release of retention.
- Notify
- In writing, with photos, before the period ends.
How it works in Ireland
Some defects only show after you live in a house: a crack as the building dries, a leak after the first storm, heating that behaves differently in winter. A defects liability period gives you a set time in the contract to have them fixed by the builder who made them.
The period begins at practical completion and the contract states how long it lasts. During it you notify defects, usually in writing, and the builder returns to fix them. Retention is normally tied to it: part is released at practical completion and the rest when the period ends and the defects have been put right.
The contract period is not your only protection. Consumer law and a claim in contract or negligence may apply beyond it, and a latent defects policy deals with a different kind of problem. Take advice if a serious defect appears late, and do not assume the end of the period ends your options.
What to ask
Before signing, ask what the period is, what counts as a defect, how you must give notice, and how fast the builder must respond. Ask what happens to retention if defects are disputed. Diarise a check towards the end, including after the first heating season, so you do not lose the chance to list problems.
A common mistake
Telling the builder by phone and relying on that. Send each defect in writing with a photo and date, and keep the replies. If a dispute follows, the paper trail is your evidence.
Diarise the end date on day one, and ask the builder to confirm in writing when the period starts. A short note in your calendar a few weeks before it ends gives you time to walk the house, list everything outstanding and send it to the builder while the contract still obliges them to act.
The full guide
This page defines the term. The guide below covers what to do about it.
Snagging your new house before final payment
How to snag a self-build in Ireland before final payment: what to check room by room, how to record defects, and retention and certificates.
Sources
Last reviewed 23 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.