Development contribution waiver: 72 days to complete your house

A house that used the temporary waiver must be complete by 31 December 2026. The Minister said on 1 October there will be no further extension.

By Published 1 min read

Timeline: the waiver scheme started on 25 April 2023, works had to commence by 31 December 2024, and houses must be complete by 31 December 2026.

In brief

  • If your self-build used the temporary development contribution waiver, it must be complete by 31 December 2026. That is 72 days from 20 October 2026.
  • If it is not complete, the council invoices the full waived contribution under the undertaking you signed.
  • On 1 October 2026 the Minister for Housing said no further extension of the schemes was proposed.
  • The waiver closed to new starts after 31 December 2024, so nobody can claim it now.
  • Ask your council in writing what evidence of completion it will accept, such as a valid Certificate of Compliance on Completion.

If your house used the temporary development contribution waiver, you have until 31 December 2026 to complete it. Counting from 20 October 2026, that is 72 days. A house that is not complete by then leaves you owing the council the full amount that was waived.

Who does this affect?

The waiver covered qualifying houses, including self-builds and one-off rural homes, that commenced on site between 25 April 2023 and 31 December 2024. It is closed to new starts, so you only need to act if you already hold a waiver approval and your house is still under construction.

If you did not use the waiver, nothing changes. Budget for the contribution condition on your permission as normal.

Will the date be extended?

Not on current information. In a written answer on 1 October 2026, the Minister for Housing said the Government did not propose to extend the schemes again. The 2024 circular had already moved the completion date once, from 31 December 2025 to 31 December 2026. Councils such as Donegal also describe the house as needing to be “completed not later than 31 December 2026” and plan to verify completed work in early 2027.

What should you do now?

  • Write down what is left: finishes, services, wastewater system and certificates.
  • Ask the council’s development contributions section, in writing, what it will accept as evidence that the house is complete.
  • Where statutory certification applies, agree the timing of the Certificate of Compliance on Completion with your certifier. The certificate of compliance guide explains the steps.
  • Ask your lender how the final drawdown fits the date. See staged drawdown.
  • If you may miss the date, speak to the council before it passes and keep the reply. There is no confirmed individual extension route, so plan for the possibility of a repayment.

The full rules, dates and clawback are in the development contribution waiver guide.

Sources

Last reviewed 20 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.

  1. Circular Letter PL 02/2024, Extension of the Temporary Development Contribution waiver and Uisce Éireann Water Connection Charge refund arrangements (30 April 2024)Department of Housing, Local Government and Heritage (copy on Tipperary County Council's site)
  2. Water Services, Parliamentary Question 130 (1 October 2026)Houses of the Oireachtas
  3. Development Contributions - Temporary Waiver SchemeDonegal County Council

News articles describe what was announced or published on the date shown. They are general information, not financial, tax or legal advice, and measures announced in a Budget may change before they become law.