Stage 1: Find and check a site

Renovate, extend or knock down and rebuild an old house in Ireland

Inherited an old farmhouse or bungalow? Compare renovating, extending or rebuilding in Ireland: planning, VAT, grants, finance and insurance.

Last reviewed 6 min read4 sources

Key points

  • Start with a survey by a building professional, not a price per square metre. The structure, damp, roof, services and energy performance decide which route is sensible.
  • Demolishing a house and building a new one is a new build for grants and for planning. Ask the council early whether it treats the site as a replacement dwelling, because rural policy can be stricter than for a renovation.
  • The Vacant Property Refurbishment Grant is for refurbishing a house that has been vacant for at least two years and was built before 2008. Permission to demolish and rebuild a new house is excluded, and the grant must be approved before work starts.
  • Construction work on a house, including extending and altering it, generally carries 13.5% VAT. Materials you buy separately are generally 23%. The rate does not change because the house is old.
  • A renovation or extension is not covered by the same insurance as a new build site. Tell your insurer what you are doing, and cover the existing structure as well as the works.
  • Lenders may treat a renovation differently from a self-build mortgage. Ask what valuation, stage payments and certification they want before you commit to a route.

Plenty of Irish self-builds start with an old house, not a bare field: a farmhouse that came down the family, a bungalow from the 1970s, or a cottage with a plot attached. The choice is the same each time. You can keep the house and renovate it, add to it, or take it down and build again. Each route changes the planning, tax, grants, finance and insurance, so choose with the numbers in front of you.

Start with a survey

Before you decide, find out what you actually have. Ask a building surveyor, an architect or a structural engineer to look at:

  • The structure: cracks, bowing walls, sagging roof lines, rotten timber and the state of the foundations.
  • Damp and ventilation: rising damp, penetrating damp and condensation each have a different cure.
  • The roof: slates, battens and felt, because a roof replacement is a big cost.
  • Services: wiring, plumbing, heating and the wastewater system, which may not meet current standards. The wastewater guide explains what a new system involves.
  • Hazards: asbestos in old roofing and lagging, and lead pipes. Removal needs specialists, and the cost can change the whole decision.
  • Energy performance: a BER assessment shows where the heat is going, and what an upgrade could achieve.

A survey costs little next to the work it can save. The architect or engineer guide explains who to ask.

Three routes compared

Renovate Extend Knock down and rebuild
Planning Often exempt for internal work, though not for a protected structure Exempt within limits, otherwise permission Permission for demolition and for a new house
Energy standard Upgrade to what is practical New part meets current rules, the old part is improved A new house meets current nearly zero-energy rules
Grants Vacant Property Refurbishment Grant and SEAI grants may apply SEAI grants may apply to the existing part Not eligible for the refurbishment grant; SEAI new-build limits apply
Surprises Hidden defects Joins between old and new Demolition waste, services and site conditions
Time Varies with the scope Varies with the scope Planning plus a full build

Use the table to decide what to ask, not as a verdict. Each house is different.

Planning for each route

Renovation of the inside of a house is often exempt from planning permission, within limits. A protected structure, or a house in an architectural conservation area, has more rules, and works that affect its character may need permission or a declaration. Ask the council.

Extensions have exemption limits that depend on floor area, height and the space left at the back. Beyond them you need permission. The planning permission guide covers the application.

Demolition and rebuild needs permission for the new house, and usually for the demolition as well. Rural areas often apply the same housing policy to a replacement as to a new one, though some plans are kinder to a replacement of a lived-in house. Read the rural housing policy guide and ask the planner before you spend money on drawings.

Grants for an existing house

  • Vacant Property Refurbishment Grant. For a house that has been vacant for at least two years and was built before 2008, where you will live or rent it out. It is approved before work starts, and permission to demolish and rebuild a new house is excluded. It pays up to €50,000, or €70,000 if the house is derelict, and only on completion: see our grant guide for the conditions and the cash gap, and apply through your local authority.
  • SEAI home energy grants. These are aimed at existing homes and help with measures such as insulation, heat pumps and solar panels. Each has its own conditions. A new house does not qualify, as the SEAI guide for new homes explains.

Grants usually require approval or registration before work starts, so do not order anything until you know.

Cost and VAT

Building work on a house, including renovating, altering and extending, generally carries 13.5% VAT. Materials you buy yourself are generally 23%. The VAT guide explains the exceptions and the two-thirds rule. Include VAT in every estimate you compare.

Add a larger contingency to a renovation than to a new build. You cannot see behind plaster or under floors until the work starts, and surprises are common. The cost guide shows how to build up a budget.

Finance for an old house

A lender’s view of a renovation differs from its view of a new build.

  • Some offer a renovation or home improvement loan, or a top-up on your existing mortgage.
  • A self-build mortgage may be possible for a major rebuild, paid in stages. The self-build mortgage guide explains how that works.
  • Lenders look at the valuation before and after, the builder and contract, and insurance.

An inherited house you own outright can give you equity to borrow against. Ask each lender early.

Insurance for an existing structure

An existing house on a building site is a different risk from a bare plot. Your normal home policy may not cover it once work starts, particularly if it is empty, and the contractor’s insurance may cover their work and not your building. Tell the insurer, and ask what covers the old structure, the works and your liability to visitors and neighbours.

The self-build insurance guide explains the covers for a new build.

When knocking down makes sense

Demolition is worth a hard look when:

  • the survey finds structural problems whose repair costs close to the cost of a new house;
  • the layout cannot be made to work, for example low ceilings and small rooms that no extension fixes;
  • you want a house that meets today’s energy standard and the upgrade of the old one would not get there; or
  • the planner confirms that a replacement is acceptable on the site.

Whichever way the sums fall, do not strip out or demolish anything until permission, grant approvals and your insurer’s agreement are in place. Work done early can end a grant claim and complicate a planning application. Keep the house when it is sound, has character you value, or when a grant makes the renovation much cheaper. Talk to the planner before you decide, because the answer on the site may rule one route out.

Questions to settle before you commit

  • A surveyor or engineer has looked at the building and given you a written report.
  • You have an estimate for each route on the same brief, with VAT.
  • The council has said what permission each route needs.
  • You know which grants apply, and what must be approved before work starts.
  • A lender has told you what it needs.
  • The insurer knows the plan, and your cover continues during the works.
  • A solicitor or tax adviser has looked at any inheritance or transfer.

Common questions

Is it cheaper to renovate an old house or knock it down and rebuild?

There is no general answer. A sound house with a good roof and structure is often cheaper to renovate. A house with damp, structural movement, asbestos or a poor layout can cost as much to repair as to replace, and a new build gives a predictable energy standard. Get a structural survey and a quantity surveyor's or builder's estimate for both routes on the same brief before you choose.

Do I need planning permission to demolish my house?

Usually yes for a habitable house, and a new house on the site needs permission as well. Ask the planning department whether you can apply for demolition and the replacement together, and what the county development plan says about replacement dwellings. Some plans ask that the old house is habitable, or require its removal.

Can I get the Vacant Property Refurbishment Grant for a house I am going to demolish?

No, permission to demolish and rebuild a new house is excluded. The grant is for refurbishing a vacant house that stays standing. It needs a vacancy of at least two years, a build date before 2008 and approval before work starts, so read the current rules on gov.ie and ask your local authority.

Do I pay VAT on renovation work?

Yes. Building, altering and extending a house is generally charged at 13.5%, while separately bought materials are generally 23%, with exceptions. The guide to VAT on self-build explains the two-thirds rule. A private owner cannot reclaim it.

Do SEAI grants apply to an old house?

Often, yes. SEAI's home energy grants are designed for existing homes, and some have an age test, such as a home built and occupied before a given year. A new house does not qualify for them. Check each grant's current conditions and get approval before you start.

Can I get a self-build mortgage to renovate?

Some lenders offer a renovation or home improvement loan, or release equity on the house, and some will lend for a major rebuild on staged payments. Terms differ, so ask each lender what it needs for your project and what the valuation looks like before and after.

Does an inherited house change the tax position?

It can. Inheritance and any later sale can have capital acquisitions tax or capital gains tax consequences. Ask a solicitor or tax adviser before you decide to sell, demolish or transfer it.

Sources

Last reviewed 20 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.

  1. Vacant homes and the refurbishment grantgov.ie
  2. Planning permissionCitizens Information
  3. Construction services (VAT)Revenue
  4. Home energy grantsSEAI

This guide is general information about self-building in Ireland, not financial, legal or insurance advice. Get advice that fits your own situation before you make decisions.