What is a wayleave for a services connection?

A wayleave is permission from a landowner for a utility to place a pole, line or pipe on or across their land, and a connection that depends on one cannot proceed until it is signed.

Last reviewed 3 sources

Quick answer

Who signs
The owner of the land the line or pipe crosses, often a neighbour.
Why it matters
ESB Networks can make it a condition of your connection quote.
Ask early
Before the quote arrives, with your solicitor checking existing rights.
Not the same as
A road-opening licence for work on a public road.

How it works in Ireland

On many one-off sites the nearest electricity line is not on your own land. If the best route for a new pole or cable crosses a neighbour’s field, the owner has to agree. That agreement is a wayleave. When one is needed, ESB Networks makes it a condition of the connection, and the work waits until it is signed.

The same idea applies to water, wastewater and your access. If a pipe or a drive has to cross land you do not own, you need the right to do so, and a lender’s solicitor will expect that right to be properly documented.

A wayleave is separate from a road-opening permission. Crossing a public road to reach a pole needs the road authority’s agreement, and ESB Networks lists road-opening permissions among the reasons a connection target can be missed.

What to ask

Before you buy the site, ask your solicitor which poles, lines and pipes cross it and whether existing rights already cover your route. Before you apply, work out the likely route and talk to any neighbour it crosses. Ask them what they would want in return and whether they will sign a standard document without delay. If the connection tracker shows your job as on hold, ask ESB Networks whether a wayleave is the item outstanding.

Also ask your solicitor who pays the legal costs on both sides, and whether the document will be registered against the neighbour’s title, since that affects how willing they are to sign.

A common mistake

Leaving the conversation until the quote says a wayleave is needed. A neighbour who feels rushed can say no or ask for a lot, while a friendly approach months earlier often goes smoothly. Treat it as part of buying the site, not a detail of the connection.

The full guide

This page defines the term. The guide below covers what to do about it.

Sources

Last reviewed 23 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.