What is an airtightness test and what result do you need?
An airtightness test (blower door test) pressurises a finished house to measure how much air leaks through the building fabric, giving an air permeability figure used for Part L compliance and the BER.
Quick answer
- Measure
- Air permeability in m³/(h·m²) at 50 Pa.
- Limit
- A maximum of 5 for new dwellings under Part L; designs usually aim lower.
- When
- Near completion, with the envelope sealed but before finishes hide leaks, ideally with a pre-test earlier.
- Who
- An independent tester with a calibrated fan.
How it works in Ireland
An airtightness test, also called a blower door test, fits a fan into an external door frame, pumps the house to a pressure difference of 50 pascals and measures how much air the fan needs to hold it there. The leakage is divided by the area of the external envelope to give the air permeability, in cubic metres per hour per square metre at 50 Pa. A lower number means a tighter house.
For new dwellings, Technical Guidance Document L sets a maximum permeability of 5 m³/(h·m²) at 50 Pa. A house that exceeds it does not comply with Part L. The BER assessor also uses the measured result in the calculation, so a tighter house scores better, and the assumed figure in your design stage BER often sits below the maximum. Many designs aim for 3 or lower, particularly with mechanical ventilation and heat recovery, which works properly only in a tight house. Ask your designer what target the energy model assumes and what the test must achieve.
The test is done near completion, when the building envelope is complete, windows and doors are fitted, service penetrations are sealed and floors, ceilings and wall linings are in place but before finishes make leaks hard to reach. Testers advise on when the house is ready. A pre-test earlier, before plastering or when the airtightness membrane is still visible, lets you find and fix leaks cheaply. Common leak points are service penetrations, the eaves and wall plate junction, around windows and doors, recessed light fittings, attic hatches and electrical sockets in external walls.
If the final test fails, you must fix the leaks and retest, which costs money and can delay the BER and the certificate of compliance on completion. The tester’s report goes to the BER assessor, and you keep a copy with the other completion records.
Choose a tester who holds a recognised qualification and uses calibrated equipment, and book early, because the test is often the last thing before the BER.
A common mistake
Leaving the first test until the house is finished. Fixing a failed result then means opening up finishes. Book a pre-test when the airtightness layer is complete but still visible.
The full guide
This page defines the term. The guide below covers what to do about it.
Meet the nZEB and Part L energy rules for your house
Plan insulation, heating and renewables to meet the nearly zero energy building (nZEB) standard. Part L targets, design checks and renovation rules.
Sources
Last reviewed 23 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.
- Technical Guidance Document L, Conservation of Fuel and Energy, DwellingsDepartment of Housing, Local Government and Heritage
- Building Energy RatingSEAI