Building a house in County Wicklow: functional need in the open countryside, the born-and-reared test and the €7,025 rural charge

Wicklow's rural housing policy: housing, economic and social need, who counts as a native of the area, the 7-year occupancy condition and the council charge.

Last reviewed 5 sources

499 single houses were completed in Wicklow in 2023 to 2025, ranking 13 of 26 counties (CSO table NDQ06).

Key points

  • Wicklow permits a house in the open countryside only for people with a demonstrable, functional social or economic need to live there, set out in Table 6.3 of the plan.
  • Social need includes people born and reared in the same rural area, returning natives, and the son or daughter of a landowner where the land has been in the family for at least 10 years. Economic need covers farm and other rural livelihoods that cannot be run from a nearby settlement.
  • A new farm or rural enterprise must have been legally and continuously running for at least 5 years, as your main income, before it counts. Businesses that are not location-dependent are not considered.
  • The council’s July 2025 update of its contribution scheme charges €3,625 for a rural house up to 150 square metres plus €68 per square metre above, so €7,025 for 200 square metres, indexed each 1 January.

Who decides, and how to apply

Wicklow County Council decides applications for the county. Its planning pages explain how to apply and let you search applications already made, which is a quick way to see how the council has treated sites near yours. The rural housing rules are in chapter 6 of the Wicklow County Development Plan 2022-2028, which was adopted in September 2022. The council varied chapter 6 in March 2026, and the plan can be varied again, so check the current text before you buy a site.

Read how a one-off house application works first. Wicklow also publishes a Single Rural House Design Guide, and objective CPO 6.44 requires rural houses to be well-designed, simple, unobtrusive and informed by it.

One test for the open countryside

Objective CPO 6.41 facilitates houses in the open countryside for those with a housing need based on a demonstrable, functional social or economic need to live there, as set out in Table 6.3. Where this conflicts with other settlement strategy objectives or landscape zones, a person who qualifies under CPO 6.41 has priority unless the house would be a likely traffic or public health hazard. Urban generated housing is not permitted in the rural areas outside the rural settlements in the settlement strategy (CPO 6.36).

Table 6.3 has three strands, and you only need one:

  • Housing need. A clear need for a new house, for example first-time owners, someone who has lost a previous home through legal separation, divorce or repossession, the transfer of a farm home to a family member or sale after emigration, or someone needing a specially adapted purpose-built house for a verified medical condition.
  • Economic need. Your livelihood is intrinsically linked to the rural area and a home there is essential to it, and the livelihood could not be kept up while living in a nearby settlement. Farmers running a significant agricultural enterprise must show that a dwelling on the holding is essential to its operation, and the council looks at whether the holding already has houses. For other rural enterprises you must show a particular feature of the work that requires living in the rural area.
  • Social need. People intrinsically linked to a rural area, including permanent native residents born and reared in the same rural area as the site; former natives returning after years away; a close relative who has inherited an agricultural holding or site; the son or daughter of a landowner where the land has been in the family for at least 10 years; people whose family home is now inside an expanded town or village boundary; and local applicants who provide care to family or work in local healthcare. Other strong social or family ties can count, case by case.

A new or alternative farm or rural enterprise, with no previous experience behind it, does not count until it has been legally and continuously running for at least 5 years before the application and is your main occupation and income. A business that is not location-dependent will not be considered. See rural housing and local need for how to assemble your evidence.

Occupancy and clusters

Under CPO 6.42, if you are granted permission you must lodge a Section 47 agreement as a burden on the property for 7 years, restricting use to you or to people who meet the CPO 6.41 criteria or others the council agrees in writing. Small settlements have their own occupancy rules (CPO 6.37 to 6.40), for example residence of 10 years in the county within 10 km for a single house in a rural cluster.

The council supports rural infill and backland houses (CPO 6.45) and houses that form a rural cluster (CPO 6.46), provided you meet the CPO 6.41 test and the design does not harm neighbours, visual amenity or rural character. Converting or reinstating abandoned buildings is supported where the original walls are substantially intact, the building has local interest and a structural survey shows it can be converted (CPO 6.43).

The development charge

Wicklow’s Development Contribution Scheme 2015, as updated on 22 July 2025, charges rural houses €3,625 per unit up to 150 square metres, plus €68 for each square metre above 150. A 200 square metre house pays €3,625 plus 50 times €68, which is €7,025. The rural rate applies to settlement levels 8 to 10 and to single local-growth houses in level 7. The scheme indexes the rates each 1 January using the CSO wholesale price index, so the amount on your permission can be higher, and the council says it is reviewing the scheme.

Extensions that do not take a rural house over 150 square metres are exempt, and the first 40 square metres of larger extensions are waived. A replacement house pays the difference between the old and new unit sizes. Retention permissions get no exemptions. The council’s page still carries the temporary waiver, but it covered only homes started on site between 25 April 2023 and 31 December 2024, so a house starting now cannot qualify. See the waiver guide.

To see how Wicklow’s charge compares, the development contributions table compares the charge for a 200 square metre house across all 31 councils.

Wastewater and site suitability

Almost every rural house treats its own wastewater, and a site that fails the test will fail the application whatever your local need. Read site suitability assessments and wastewater treatment systems before you pay for the test.

Apply or search applications: Wicklow County Council

The national guides behind this page

The rules here apply on top of national law. These guides explain each step in full.

Common questions

Does ‘born and reared’ mean exactly the same rural area as the site?

For the native-resident and returning-native categories, the plan says you were born and reared in the same rural area as the proposed site. Other social need categories rely on strong social or family connections that you can evidence, assessed case by case.

My parents’ land has been in the family for less than 10 years. Does that rule me out?

The plan’s landowner’s-child category specifically requires the land to have been in family ownership for at least 10 years before you apply. You might still qualify under another category, such as native resident, so take pre-planning advice.

Can I start a farm or business to qualify?

Only after it has been legally and continuously running for at least 5 years before you apply, and is your primary occupation and source of income. The plan will not accept a business that is not location-dependent.

Which charge applies, the 2015 figure or a newer one?

The council’s update of 22 July 2025 sets the rural rate at €3,625 up to 150 square metres plus €68 per square metre above. The scheme adjusts rates each 1 January, so the amount on your permission can be higher. The council says it is reviewing the scheme.

Sources

Last reviewed 23 October 2026. Rules and figures change, so confirm anything important with the source before you rely on it.

  1. Wicklow County Development Plan 2022-2028, chapter 6 Housing, as varied March 2026Wicklow County Council
  2. Wicklow County Council Development Contribution Scheme 2015, updated 22 July 2025Wicklow County Council
  3. Wicklow County Council: Development Contribution SchemeWicklow County Council
  4. Wicklow County Council: planningWicklow County Council
  5. CSO New Dwelling Completions (NDQ06), single houses by local authorityCentral Statistics Office

This page is general information about building in Wicklow, not legal or planning advice. Your own site, the exact wording of your permission and the council’s current documents decide your case. Ask the council or a planning consultant before you rely on it.